Intro
Jan 2011 sprint plan:
- Staging Release: Jan31, 2011
- Production Release: Feb 3, 2011
Plan
NOTE: Please note that the task 2397 for Andriy was completed and be a part of Jan 6 released. It is still pending for Roma to test. Total hrs for this sprint with rmhR = 406
Weekly updated Plan Jan 14
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
Weekly updated Plan Jan 21
NOTE: Due date for .rmhR, it must be updated by the end of Thursday. Per Sasha and Kostya, ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. Task 2721 has been created: purchase ZK lib
Mantis: 2576, 2301, 2398, 2419, and 2507
Weekly updated Plan Jan 28
NOTE: Due date for .rmhR, it must be updated by the end of Thursday.
ZK task and related tasks are requested to postpone to the next sprint because of the purchasing license. Task 2721 has been created: purchase ZK lib
Mantis: 2576, 2301, 2398, 2419, and 2507
Weekly updated Plan Feb 4
NOTE: Staging - Jan 31, Production - Feb 3