SA re defined part 3

From UG

(Difference between revisions)
Jump to: navigation, search
(%BA %SA %Dev %QA %UAT %WU mantis fields)
Line 5: Line 5:
This is a 3rd part of the article. Previous: [[SA re defined part 2]]
This is a 3rd part of the article. Previous: [[SA re defined part 2]]
-
== Weekly Status update meetings ==
+
== Monthly BA and SA planning process ==
-
== %BA %SA %Dev %QA %UAT %WU mantis fields ==
+
I introduce monthly plans for BAs and SAs.
 +
 
 +
See examples under [[:Category:Proj Plans]]
 +
 
 +
== Weekly Status update ==
 +
 
 +
Once a week everyone should update task status. Steps:
 +
 
 +
* BA, SA, Developer, QA must update [[%Percent Complete mantis fields]]
 +
* BA must post updated spreadsheets into [[:Category:Proj Plans]] and email to management
 +
* request meeting (if required) to resolve potential problems
 +
 
 +
== Percent Complete mantis fields ==
These fields indicate estimated % of task completed. Examples: 5% - just started; 100% - fully completed
These fields indicate estimated % of task completed. Examples: 5% - just started; 100% - fully completed
-
Should be updated once a week before [[#Weekly Status update meetings]]
+
Should be updated once a week before [[#Weekly Status update meetings]].
  %BA - to be set by BA
  %BA - to be set by BA

Revision as of 17:43, 23 December 2010


Contents

Intro

This is a 3rd part of the article. Previous: SA re defined part 2

Monthly BA and SA planning process

I introduce monthly plans for BAs and SAs.

See examples under Category:Proj Plans

Weekly Status update

Once a week everyone should update task status. Steps:

Percent Complete mantis fields

These fields indicate estimated % of task completed. Examples: 5% - just started; 100% - fully completed

Should be updated once a week before #Weekly Status update meetings.

%BA - to be set by BA
%SA - to be set by SA
%Dev - to be set by Developer
%QA - to be set by QA engineer
%UAT - to be set by BA
%WU - to be set by BA