=== week 4: June 28 Mon - July 2 Fri === | === week 4: June 28 Mon - July 2 Fri === | ||
- | // | + | * continue coding and QA |
+ | * start UC testing | ||
+ | |||
+ | * '''Tue 10pm:''' Kiev/NY status update | ||
+ | * '''Thur 10pm:''' Kiev/NY status update | ||
+ | |||
+ | :* requirements: 99% done | ||
+ | :* design: 99% done | ||
+ | :* documentation: 90% done | ||
+ | :* coding: 60% done | ||
+ | :* QA: 50% done | ||
+ | |||
+ | === week 5: July 5 Mon - July 9 Fri === | ||
+ | |||
+ | * complete coding and QA | ||
+ | * complete UC testing | ||
+ | * Create User Guide, Rollout Schedule, Training Plan, Support plan | ||
+ | |||
+ | * '''Tue 10pm:''' Kiev/NY status update | ||
+ | * '''Thur 10pm:''' Kiev/NY status update | ||
+ | |||
+ | :* documentation: 99% done | ||
+ | :* coding: 99% done | ||
+ | :* QA: 99% done | ||
+ | |||
+ | === week 6: July 12 Mon - July 16 Fri === | ||
+ | |||
+ | * QA on staging | ||
+ | * Release | ||
+ | |||
+ | * '''Tue 10pm:''' Kiev/NY status update | ||
+ | * '''Thur 10pm:''' Kiev/NY status update | ||
+ | |||
+ | === week 7: July 19 Mon - July 23 Fri === | ||
+ | |||
+ | * First week of release | ||
+ | |||
+ | * '''Tue 10pm:''' Kiev/NY status update | ||
+ | * '''Thur 10pm:''' Kiev/NY status update | ||
== Project plan and do list == | == Project plan and do list == |
Revision as of 02:00, 20 June 2010
Contents |
About this doc
This wiki provides all Proj Management info for Cybertrax 2.1 Client project.
Project documentation
All information is gathered and structured in several wikis under Category:Cybertrax 2.1 Client
Project communication
All communication is done through:
- mantis
- Skype
All mantis tasks are under this parent: http://mantis.jaguarfreight.com/mantis/view.php?id=2077
Project team
Project business processes and tools
Project update meetings
- who must attend: Andrei, Sasha, Alex, Denise
- Tuesd, Thursd 10-11am
- Skype chat
- Coordinator on NY side / Host: Alex
- Coordinator on Kiev side: Andrei
Project broadcasts and forum
- Broadcasts / News posted into mantis: http://mantis.jaguarfreight.com/mantis/view.php?id=2127
- Questions / answers should be posted there as well or we will use wiki discussion, see http://en.wikipedia.org/wiki/SummarizeDiscussion
Project schedule
week 1: June 7 Mon - June 11 Fri
- meetings with clients
- preliminary design sessions
- requirements: 50% done
- design: 30% done
- documentation: 10% done
- coding: 0% done
- QA: 0% done
week 2: June 14 Mon - June 18 Fri
- analyze requirements
- invent design
- write detailed documentation
- Wed 2pm: send draft to Simon, Marc
- Fri 4pm: send ver 1.0 to Bill
- requirements: 80% done
- design: 70% done
- documentation: 60% done
- coding: 5% done
- QA: 0% done
week 3: June 21 Mon - June 25 Fri
- finalize requirements
- finalize design
- improve documentation
- define tasks for every developer
- start coding and QA
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- requirements: 95% done
- design: 90% done
- documentation: 80% done
- coding: 30% done
- QA: 20% done
week 4: June 28 Mon - July 2 Fri
- continue coding and QA
- start UC testing
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- requirements: 99% done
- design: 99% done
- documentation: 90% done
- coding: 60% done
- QA: 50% done
week 5: July 5 Mon - July 9 Fri
- complete coding and QA
- complete UC testing
- Create User Guide, Rollout Schedule, Training Plan, Support plan
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
- documentation: 99% done
- coding: 99% done
- QA: 99% done
week 6: July 12 Mon - July 16 Fri
- QA on staging
- Release
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update
week 7: July 19 Mon - July 23 Fri
- First week of release
- Tue 10pm: Kiev/NY status update
- Thur 10pm: Kiev/NY status update